hi folks, i'm running 12x s21 xps pulling 13.5w/th at my facility. bitmain pushing these s23 hydros at 9.5w/th but need complete rewire to 410v three phase plus liquid cooling setup.
did the math:
current setup: 12 units x 277th = 3324th total
upgrade option: 6 units x 580th = 3480th total
gain: 156th more hash
cost: 6x$9000 = $54k plus $25k infrastructure
payback at 6 cents/th: 79000/9.36 = 8440 days
am i missing something or is this upgrade financially insane?